How to Remove an Old Driveway Before Installing a New One

A complete guide to how to remove an old driveway before installing a new one — what homeowners need to know.

⏱️ 14 min read
💰 High-end material
💎 Premium quality
Get Free Estimate
📋 Table of Contents

Why Removing Your Old Driveway the Right Way Matters

Ripping out an aging driveway looks simple on social media—hook a chain to the bumper, give it a tug, and haul the chunks away. In real life, a hasty demo can crack foundations, sever utility lines, and leave you with a lumpy base that ruins the new pavement within months. Taking time to plan, inspect, and execute each step protects your property, keeps you code-compliant, and saves thousands in surprise repairs.

This guide walks you through the entire process: permits, tools, safety, responsible disposal, and site prep for the new surface. Whether you hire a pro or tackle part of the work yourself, you’ll know exactly what “done right” looks like.

Step 1: Check Rules, Lines, and Timing

Call 811 and Local Building Offices

Underground electric, gas, and fiber-optic lines often cross front yards. A free 811 call (or online ticket) gets utilities marked within 2–3 business days. Wait for the paint to dry—literally—before you swing a pick or start a saw. Many cities also require a demolition permit ($25–$150) and an inspection before new base material can be brought in.

HOA & Street Closure Notices

Homeowners associations may restrict hours, dumpster placement, and even the color of the new concrete. If the driveway touches a public alley or sidewalk, you might need a temporary street-use permit for the dumpster or skid-steer access.

Choose the Right Weather Window

Plan for two consecutive dry days. Rain turns excavated soil to mud and doubles haul-off weight (you pay by the ton). Temps below 40 °F slow concrete demolition and can freeze water in expansion joints, making breakage harder.

Step 2: Gather Tools, Machines, and Safety Gear

DIY Tool List (for Small Asphalt or Concrete Pads)

  • 12-lb sledgehammer and 3-ft pry bar
  • Electric or pneumatic jackhammer (1500–1800 W, 60-lb class)
  • Concrete saw with diamond blade (gas or 15-amp electric)
  • Wheelbarrow, bolt cutters (for wire mesh), and heavy-duty tarp
  • PPE: ear muffs, ANSI-rated safety glasses, respirator ( silica-rated P100), steel-toe boots, and cut-resistant gloves

When to Bring in Machines

Driveways larger than 500 ft² or thicker than 4 in. eat up weekends fast. A skid-steer with a hydraulic breaker can chew 100 ft² per hour; a mini-excavator with a thumb removes broken chunks in half the time. Rental yards typically bundle delivery, fuel, and a 4-hour training primer—budget $350–$500 per day.

Disposal Containers

Concrete and asphalt weigh 100–150 lb per ft³. A 10-yd roll-off holds roughly 8–10 tons—enough for a standard 2-car (18 × 20 ft) 4-in. slab. Order an extra 2 yd of capacity to avoid overflow fees.

Step 3: Isolate Utilities and Protect Structures

Mark the Perimeter

Spray-paint a line 6 in. inside the edge you plan to break. This “relief joint” prevents fractures from running into garage floors, sidewalks, or porch pads.

Disconnect Power to Gate Openers, Lighting, and Snow-Melt Systems

Shut off breakers, cap wires in junction boxes, and photograph the routing for re-installation later. Cutting a 240-V snow-melt cable accidentally can add $1,000+ to the project.

Temporarily Support Nearby Fences and Mailboxes

Drive 2×4 stakes at 45° angles to keep posts from shifting when the breaker hammer vibrates the soil.

Step 4: Break Up the Surface

Score First, Then Break

Use a concrete saw to cut 2-in. deep grooves every 2 ft in both directions. The score lines guide cracks and yield manageable 2×2 ft pieces you can lift without machinery.

Start at the Corner, Work Inward

Begin at the weakest point—usually the outer edge nearest the street. Position the jackhammer at a 45° angle; let the tool’s weight do the work. Every 10 minutes, pause and pry loose pieces free to reduce binding.

Asphalt Shortcut

Asphalt is softer; a 60-lb jackhammer on low throttle plus a spade shovel is often enough. Cut perimeter edges with a circular saw fitted with an abrasive blade to leave crisp lines against garage aprons or sidewalks.

Step 5: Lift, Load, and Haul

Team Lift or Mechanical Thumb

Concrete slabs 2×2 ft × 4 in. weigh 200 lb—too heavy for one person. Use a dolly, walk-behind forklift attachment, or rent a skid-steer with a grapple bucket.

Sort Materials for Savings

Clean concrete (no rebar, trash, or asphalt chunks) is often accepted as “#57 recycle” at $5–$10 per ton instead of $75 per ton landfill rates. Separate loads on site to cut disposal fees in half.

Track Weight Tickets

Keep scale tickets from the landfill or recycler; compare totals to your contractor’s invoice to verify you weren’t charged for “phantom” tonnage.

Step 6: Excavate the Sub-Grade

Go Deep Enough for the New Surface

  • Concrete: 4-in. slab + 4-in. base = 8 in. total
  • Asphalt: 3-in. surface + 6-in. base = 9 in. total
  • Pavers: 2 ⅜-in. paver + 1-in. bedding + 6-in. base = 9 ⅜ in. total

Check Soft Spots

Probe every 2 ft with a ½-in. rebar rod. If the bar sinks easily, remove the spongy soil and refill with compacted crushed stone. Skimping here causes settlement cracks within a year.

Slope for Drainage

Maintain a 1 % grade (⅛ in. per foot) away from garages and foundations. A $30 laser level or string-line makes the check quick.

Step 7: Eco-Friendly Disposal Options

Recycle Concrete into Road Base

Many asphalt plants accept clean concrete, crush it, and mix it into new aggregate. Some will pick up 10-ton loads free if you deliver within 15 miles.

Repave in Place (Full-Depth Reclamation)

For failed asphalt drives, a paving contractor can pulverize the existing surface and 4–6 in. of base, add cement powder, and roll it into a stabilized base. You skip haul-off entirely and cut virgin material use by 80 %.

Donate to Community Projects

Habitat for Humanity ReStores and local garden clubs often accept intact pavers or brick for walkways—tax-deductible and landfill-free.

Pro vs. DIY: When to Bring in Drivewayz USA

Cost Comparison

National average for full removal and disposal runs $2–$4 per ft² for asphalt and $3–$6 for reinforced concrete. On a 600 ft² drive, DIY can save $1,000–$1,500 if you already own a truck and have two strong helpers. Add $400–$600 for jackhammer rental, $300 for the dumpster, and $100 in permits—savings shrink fast.

Risk Factors Better Left to Pros

  • Driveway abuts a basement foundation wall
  • Rebar is epoxy-coated or post-tensioned (dangerous snap-back)
  • County requires truck scale tickets and recycled-content reporting

Questions to Ask a Contractor

  1. “Will you provide a detailed line-item for haul-off tonnage?”
  2. “Do you carry both general liability and underground utility insurance?”
  3. “Can you schedule the removal and base installation the same day to avoid erosion?”

Step 8: Final Site Prep for the New Driveway

Compact in Lifts

Add crushed stone in 3-in. lifts, watering lightly and compacting each pass with a plate compactor (pass once every square foot). A minimum 95 % Standard Proctor density locks out future settling.

Install Geotextile Fabric (Optional but Smart)

Woven fabric between sub-grade and base stone prevents migration and reduces required base thickness by 1 in.—often paying for itself in rock savings.

Final Grade Check

Stretch a string line across the width; measure at mid-point to confirm ¼-in. crown for asphalt or dead-flat for concrete with controlled joints. Snap chalk lines so your paving crew hits the marks exactly.

Frequently Asked Questions

Most cities treat demolition as a “land-disturbing activity,” so yes—expect a $25–$150 permit. The same permit usually covers replacement, so file once and avoid double fees.

Generally no. Burial is considered illegal fill in many counties and can trigger fines or resale issues. Recycled concrete is cheaper to dispose of and keeps you code-compliant.

A standard 600 ft² reinforced concrete drive takes 4–6 hours with a skid-steer and crew of two, plus another 2 hours for loading and final grading. DIY with a jackhammer: plan a full weekend and recruit strong helpers.

Shut off the main valve immediately, call the utility’s emergency line, and document the damage. If you called 811 first and the line was mis-marked, the utility bears repair cost; if you skipped the call, you do.